Formal Construction Bid Qualification Question

  • Purchasing Director
    Guilford County
    2
    A bidder has submitted a bid price that is lower than the schedule of values submitted as part of the bid package. In addition, the schedule of values has missing line items that appear to be lumped into one line item.  Does this constitute a material defect and rejection of the bid? 